Project creation delays in AP regions
Resolved

Project creation has returned to normal. The issue is now resolved.

Wed, Jul 8, 2026, 03:30 PM
(4 months ago)
·
Affected components

No components marked as affected

Updates

Resolved

Project creation has returned to normal. The issue is now resolved.

Wed, Jul 8, 2026, 03:30 PM

Monitoring

Recovery has continued and project creation in the relevant region has returned to normal. We will continue to monitor this for another 30 minutes.

Wed, Jul 8, 2026, 02:59 PM(30 minutes earlier)

Identified

Project creation is recovering. We are actively tracking recovery.

Wed, Jul 8, 2026, 02:42 PM(17 minutes earlier)

Identified

We have identified options for mitigation and are discussing the best implementation methods for them.

Wed, Jul 8, 2026, 02:12 PM(29 minutes earlier)

Identified

We continue our investigation into how to mitigate the project creation delays. We are examining relevant data paths in detail.

Wed, Jul 8, 2026, 01:44 PM(28 minutes earlier)

Identified

We have identified the cause of the creation delays and are actively working to address the problem.

Wed, Jul 8, 2026, 01:17 PM(26 minutes earlier)

Investigating

We are aware of project creation taking longer than normal in AP regions. A retry should enable completion of creation for those impacted. NOTE: This incident is not related to the ongoing capacity issues incident we are monitoring.

Wed, Jul 8, 2026, 12:52 PM(24 minutes earlier)